Gov Abba Kabir Vow to complete 5 Kilometre road projects across the state

#Zulum238Projects #Term2 Focus: Education (54 Projects) Zulum's 5th year in office, consolidating on sterling 4 years of the first tenure. “1,195 Projects and Counting.” Series on 238 projects in the first year of the second tenure of Governor Zulum.

By Rabiu Sanusi

Kano state government has concluded arrangement complete the abandoned 5 kilometers rural road project commissioned across the 44 local government areas of the state.

Google search engine

Governor Abba Kabir Yusuf gave the assurance Tuesday after a reconciliation meeting with contractors handing the capital projects at the government house.

The multi-million naira 5 kilometers rural urban road projects which were awarded by former Governor, Dr. Rabiu Musa Kwankwaso during his administration had suffered total neglect by immediate past administration of Abdullahi Umar Ganduje.

“Ganduje’s failure to complete his predecessor’s developmental and public oriented projects had left the direct beneficiaries in excruciating pain, having left the project in bad sharp through out eight years of his administration.

Governor Abba Yusuf also commended the contractors for their timely response, assured his administration’s resolve to sustain Dr. Kwankwaso’s rational behind road infrastructure.

As Triumph Newspaper report a Critical of mutual agreements reached after the meeting include immediate mobilization of the handlers back to sites in the next one week to complete the project.

See also  Dangote: Fuel Imports End in 4 Weeks

Other resolutions concluded between the two parties are, the urgent directive issued to state Ministry of Land and Physical Planning to sort out issues of pending compensation problem.

” It was resolved that contractors would meet with their respective banks to access 30 per cent advance payment released to the contracts but failed to access it.”

” It was further resolved a result of recorded escalation in the prices of construction materials, that government has accepted to review the cost of the remaining items of works based moderate upward reviewed rates.

” It was also agreed that goverment would fashion out a planned strategic payments to contracts on monthly basis such that no payment is stagnated.

The resolution had that contractors that accepted the new offer should mobilize to their respective sites within one week otherwise forfeit the opportunity.